The City created the infrastructure projects dashboard as an additional resource to keep the public informed of infrastructure projects occurring in the City. The dashboard provides a graphical depiction of how much work is being done and how much money is being spent by the City to improve the community. 

Please note that project details, including timelines, scope, and other relevant information are subject to modification as needed.

News

Resurfacing Update: December 1, 2025

Post Date:12/01/2025 3:33 PM

BLOOMINGTON, IL - The City of Bloomington provides regular updates on resurfacing work throughout the construction season. The most recent update is included below.

For more information on roadwork in the City of Bloomington, visit www.bloomingtonstreets.com, e-mail engineer@cityblm.org or call 309-434-2980 during regular business hours. Residents can also sign up for e-mail or text updates for Bloomington Streets by visiting www.bloomingtonil.gov/subscribe and subscribing to Bloomington Streets.

FY25 Resurfacing

G.E. (General Electric) Rd, west of Hershey to Towanda Barnes

Stage 1: (west of Hershey to Airport)

  • Resurfacing has been completed

Stage 2: (Airport to Towanda Barnes)

  • Resurfacing has been completed

FY26 Resurfacing

E. Oakland Ave, west of Prospect through Hershey

  • Installation of the asphalt surface course has been completed
  • Final adjustment and installation of the underground utility castings has been completed
  • Restoration of selected driveway approaches has been completed
  • Installation of pavement striping is scheduled to be completed in spring 2026

Prospect Rd, Oakland to Empire

Stage 1: S. Prospect Rd. (Oakland to Washington)

  • Installation of the asphalt surface course has been completed
  • Removal and replacement of the concrete items (sidewalk; ramps) has been completed
  • Restoration of selected driveway approaches has been completed
  • Final adjustment and installation of the underground utility castings has been completed
  • Installation of pavement striping is scheduled to be completed in spring 2026

Stage 2: N. Prospect Rd. (Washington to Empire)

  • Installation of the asphalt surface course has been completed
  • Removal and replacement of the concrete items (sidewalk; ramps) has been completed
  • Restoration of selected driveway approaches has been completed
  • Final adjustment and installation of the underground utility castings has been completed
  • Installation of pavement striping is scheduled to be completed in spring 2026

E. Washington St, Veterans through Hershey

  • Installation of the asphalt surface course has been completed
  • Restoration of selected driveway approaches has been completed
  • Removal and replacement of the concrete items (sidewalk; ramps) has been completed
  • Final adjustment and installation of the underground utility castings has been completed
  • Installation of pavement striping is scheduled to be completed in spring 2026

Constitution Trail, Fox Creek bridge over the Interstate to Morris

  • Resurfacing has been completed

Contact:
Katherine Murphy
Communications & External Affairs Mgr.
Phone: 309-434-2241
Email: kmurphy@cityblm.org

Contact:
Jim Karch
Director of Engineering
Phone: 309-434-2980
E-mail: engineer@cityblm.org

Return to full list >>

Calendar